President Pakistan Businessmen & Intellectuals Forum (PBIF), All Karachi Industrial Alliance and First Vice Chairman of the Businessmen Panel of FPCCI Mian Zahid Hussain on Wednesday said delay in critical reforms in the energy sector has the potential to bankrupt country.
The official power sector losses which are Rs 320 billion are over half of the amount allocated in federal developmental budget while independent experts view losses at Rs 370 billion, he said.
The circular debt is at Rs 661 billion while theft and wastage has increased from 18.6 percent to 18.7 percent, said Mian Zahid Hussain.
He said that NEPRA has allowed power distribution companies to recover 15.2 percent losses from consumers who were earlier paying 13.1 percent of the total losses.
Mian Zahid Hussain said that sale of DISCOs might have improved situation which has been delayed by nine months.
Some bureaucrats in the gas utilities are failing LNG project, said the Former Minister, adding that agreement for import of gas has been delayed by nine months.
Government is supposed to pay around 30 million rupees as terminal charges per day which is not being utilised therefore authorities should accept their inability and allow private sector to import gas.
He said that pipelines have the capacity of transport imported gas which is not being used otherwise gas companies can generate extra revenue.